°ÄÃÅÁùºÏ²Ê×ÊÁÏ¿â

East Side Access CM006

Manhattan North Structures

Project Details

TUTOR PERINI AFFILIATES


Prime Contractor
Contract Amount: $446 Million


Electrical Subcontractor
Contract Amount: $21 Million

OWNER
NYC Metropolitan Transportation Authority

LOCATION
New York, NY

ARCHITECT
GEC (PB/STV/Parsons)

SIZE
3 Miles

COMPLETION
2019

Project Description

The MTA's East Side Access Project is a multi-billion dollar infrastructure project designed to bring Long Island Railroad to Grand Central Station in New York City.ÌýThis contract, the Manhattan North Structures Package, involved the installation of permanent structural concrete lining and fit-outs within tunnels, caverns, and interior structures. The existing tunnels run from just north of Grand Central Terminal located in Manhattan to Long Island City, Queens. CM006 also included the rehabilitation of the 63rd Street Tunnel and construction of the 63rd Street Tunnel duct bench.

Work included threeÌýmiles of tunnels and caverns between Queens and Grand Central Station in Manhattan, 1,500 concrete placements totaling 70,000 cubic yards, 11,000 linear feetÌýof tunnel lining, threeÌýunderground caverns, twoÌýmulti-level underground structures, 24,000 linear feetÌýof cast-in-place concrete duct bench, 1,000,000 square feetÌýof PVC waterproofing, and 5.6 million pounds of reinforcement steel.

Ìý

RELATED PROJECTS
ESAÌýCH053 (Harold Structures Part 1)
ESAÌýCH054A (Harold Structures Part 2)
ESAÌýCH057 (Harold Structures Part 3)
ESAÌýCH061A (Michaels – Track A Cut & Cover Structures)
ESAÌýCM005 (Manhattan South Structures)
ESAÌýCM007 (Grand Central Terminal Caverns)
ESA CM014B (Grand Central Terminal Concourse Facility and Fit-Out)
ESAÌýCQ031 (Queens Bored Tunnels)

ESAÌýCQ032 (Queens Structures and Plaza Substation)
ESAÌýCQ033 (Mid Day Storage Yard)
ESA CS086 (Systems Package No. 3)
ESAÌýCS179 (Systems Facilities Package No. 1)